Streets and sidewalks will be removed and replaced between 6th and 8th streets
NEWS RELEASE
City of Edmond PO Box 2970 Edmond, OK 73083
Friday, Dec. 8, 2023
Sections of Littler Avenue, between 6th and 8th streets, will be closed to traffic beginning Monday, Dec. 11, while work to replace the concrete paving and replace sidewalks is completed.
Part of the FY23 Concrete Paving reconstruction project, short sections of the impacted streets will be closed while work is completed. Each section closure is expected to last approximately 10 days, with cooperative weather. Streets and the adjacent drives will have the concrete paving removed and replaced. Street section work will begin on Littler at 8th and move north to just north of 7th. Sidewalk replacement work will run along the east side of Littler and run from 6th to 8th.
Residents in the area will not have street access in the closed sections and will be required to park outside of the closed area. There will be no through traffic access in the closed sections. Residents and motorists are asked to be aware and adjust their travel plans accordingly.
The cost of this project is $982,090.